Cameroon’s Minister of Public Works, Emmanuel Nganou Djoumessi, has officially signed Contract No. 0983 (dated July 1, 2026) allocating the technical oversight and supervision duties for the upcoming bituminous surfacing project in the Fako Division to NSM & FILS SARL.
Key Project Details
Contract Value: 79,924,928 FCFA (tax inclusive)
Execution Period: 11 months
Project Scope: Technical monitoring of asphalt surfacing along the 13-kilometer stretch covering Bwiteva – Bokova – Bonakanda – Bova – Buea Town – Governor’s Junction.
Funding Source: Ministry of Public Works (MINTP) Public Investment Budget across the 2026 and 2027 fiscal cycles.
Procurement Framework: Formalized under Mutual Agreement Authorization No. 00703-26-26/L/PRC/MINMAP/SG/DGMI/DMTR/BECA, issued on January 29, 2026.
During the bidding phase, competing firm GAMES SERVICES ENTERPRISE was disqualified after failing to provide the mandatory bid bond. The designated firm, NSM & FILS SARL, has been instructed to contact the Department of Contracts within the Ministry of Public Works to finalize and execute the contract agreement.
Socio-Economic Impact
This critical urban and peri-urban corridor serves as a primary transport link within the South West Region's capital. Upgrading the 13-kilometer stretch to bituminous concrete will streamline local traffic flows, substantially lower commute durations, and stimulate trade and movement across neighboring local communities.